COMMONWEALTH OF MASSACHUSETTS
DEPARTMENT OF TELECOMMUNICATIONS AND ENERGY
CABLE TELEVISION DIVISION
MediaOne of Massachusetts, Inc.,
MediaOne Group, Inc., and AT&T Corp.,
Appellants,
v.
Board of Selectmen of the Town of North Andover,
Mayor of the City of Quincy,
City Manager of the City of Cambridge,
and the Mayor of the City of Somerville,
Appellees. |
CTV 99-2;
CTV 99-3;
CTV 99-4;
CTV 99-5 |
JOINT OPPOSITION OF TOWN OF NORTH ANDOVER, CITY
OF QUINCY, CITY OF CAMBRIDGE AND CITY OF SOMERVILLE TO
APPELLANTS' MOTIONS FOR SUMMARY DECISIONS
Introduction
Procedural Background of the Cases
A. The MediaOne/AT&T Merger and
Application for Change in Control
B. Regional Hearings
C. AT&T/MediaOne Presented Its
Open Access Position In Public Hearings
D. The Issuing Authorities' Hearings
and Decisions
- The City of Cambridge
- The City of Quincy
- The Town of North Andover
- The City of Somerville
E. AT&T's Appeals
The Open Access Issue Is Central To These Appeals
A. Open Access on Broadband - This is the Way
B. The Importance Of Open Access In The Current Cable Debate
C. Denial of Open Access Is Harmful to Robust Competition
D. The Portland Litigation
E. AT&T's Recent Commitment To "Open Access"
- AT&T's December 6 Promise to the FCC
- "Open Access Lite"
- AT&T Should Not Be Permitted To Dictate the Timeline
Argument
A. The Summary Decision Standard Has Not Been Met 23
B. Application of the Regulations to Exclude Consideration of Open Access Exceeds the
Division's Authority 27
- If applied to preclude consideration of open access, the regulations as applied are
contrary to Congressional intent and federal law
- The regulations as applied are inconsistent with the purposes of G.L. c. 166A
C. The Division Should Waive Regulation 4.04 For Consideration Of Open Access In The
Transfer Decision 33
1. The negative effects on competition of this transfer justify the waiver of
Regulation 4.04
2. AT&T received sufficient notice and opportunity to address the issue of open access
D. Regulation 4.04 Substantially Impairs the Issuing Authorities' Contractual Rights
E. Regulation 4.04 Should Not Be Applied Retroactively 39
F. Conditional approval is an appropriate exercise of the Issuing Authorities'
pre-existing rights under the license agreements 41
G. Failure to Provide Open Access Involves Appellant's Legal Ability and Technical
Expertise to Operate the Cable System under the Existing License. 42
- AT&T's legal ability 42
a. The Issuing Authorities retain the power provided by federal legislation to promote
competition 42
b. AT&T's failure to provide open access adversely affects competition and implicates
restraint of trade provisions 43
- AT&T does not maintain or is unwilling to utilize the technical expertise to perform
this contract in a lawful manner. 45
- Cambridge's denial based upon the additional consideration of the transferee's lack of
management experience and failure to adhere to the existing license is appropriate grounds
for denying AT&T's transfer request. 48
Conclusion
JOINT OPPOSITION OF TOWN OF NORTH ANDOVER, CITY
OF QUINCY, CITY OF CAMBRIDGE AND CITY OF SOMERVILLE TO
APPELLANTS' MOTIONS FOR SUMMARY DECISIONS
Introduction
The Town of North Andover, the City of Quincy, the City of Cambridge, and the City of
Somerville (collectively the "Issuing Authorities" or "Appellees")
oppose the Motions for Summary Decision that MediaOne of Massachusetts, Inc., MediaOne
Group, Inc. (collectively "MediaOne") and AT&T Corp. ("AT&T")
(collectively, the "Appellees") have filed in each of the above referenced
matters pursuant to 801 CMR 1.01(h).
To obtain summary decision, Appellants maintain the burden of establishing that the
facts and law at issue are undisputed to the extent that the papers filed show that a
hearing can serve no useful purpose. The record before the Division demonstrates, however,
that not only are there significant issues of material fact and law but also that these
facts and the law weigh heavily in favor of Division approval of the Issuing Authorities'
transfer decisions.
As explained below, the decisions by the Issuing Authorities were each an appropriate
exercise of the power granted them by federal legislation and consented to by the
Massachusetts Legislature to promote competition in the field of cable services and for
the purpose of protecting consumers. To the extent that the Division regulations are
interpreted narrowly to preclude consideration of the requirement of open access, and the
Division does not waive application to accommodate such consideration, the regulations are
inconsistent with the applicable federal and Massachusetts statutes and must be found
invalid.
Finally, the application of the regulations to preclude consideration of open access is
contrary to the contractual rights reserved to Cambridge, Somerville, and North Andover
under their respective franchise agreements. To so impair these contracts would violate
constitutional protections and inappropriately apply later enacted regulations
retroactively. For all of these reasons, the Division must allow for the Issuing
Authorities' consideration of open access in the transfer decision.
The above captioned appeals all revolve around AT&T's claim that the cable wire
franchises it is absorbing entitle it to become an unconstrained master of a constricting
bottleneck in the Internet. The immediate concern of supporters of open access is
AT&T's forced bundling of its preferred and captive ISP with its wire franchise. But
what is more broadly at risk is the very integrity of the Internet's design. Since 1975,
when the architecture of the current Internet was laid out, the numbers of users has
increased by nearly a millionfold; the power of computers has increased by 1000 times
while their cost has dropped to one thousandth; the communications links that make up the
network have increased in speed by a million times; and the Internet is being used in ways
completely undreamed of at the time of its design. As Massachusetts Institute of
Technology Computer Science Professor Jerome Saltzer lucidly explains, "[t]his
remarkable evolution and adaptation has been made possible by one simple design principle,
called the End-to-End argument. The End-to-End argument says 'don't force any service,
feature, or restriction on the customer.'"
<http://web.mit.edu/Saltzer/www/publications/openaccess.html>
The Issuing Authorities either denied or conditionally approved AT&T's FCC Form 394
transfer requests that AT&T filed in connection with its takeover of MediaOne, the
largest supplier of cable television services in the Commonwealth. Each of the Issuing
Authorities relied upon AT&T's refusal to permit open access to its broadband network
as one basis for their respective decisions. AT&T now seeks a lightning fast decision
from the Division on this important public policy issue that will preserve or enhance
AT&T's emerging monopoly in the market for high speed Internet connections in this
state and around the country. AT&T has not met its burden with regard to summary
disposition. The Issuing Authorities were within their legal rights in considering open
access and concluding that the transfer must allow for open access.
AT&T's request for summary disposition is further undermined by its announcement on
December 6, (made after these appeals were filed) that AT&T will provide some form of
open access to its developing cable broadband empire in the year 2002. While vague and
non-binding, this announcement belies AT&T's consistent and repeated testimony in
public hearings across Massachusetts that open access was technically impossible,
economically infeasible to implement and contrary to the interests of the consumers.
AT&T has now conceded the reasonableness of the Issuing Authorities' open access
conditions. Accordingly, any attempt by AT&T to summarily dispose of this action must
itself be summarily dismissed.
Summary disposition is also inappropriate given the transformative nature of these
transfer proceedings. The Issuing Authorities all granted initial licenses to cable
television suppliers to establish community antennas and cable networks through the
streets of each community so that the residents in each municipality would have better
access to television programming. Technology now permits this access to be transformed
from a connection to a community television antenna into a pipeline for the Internet. The
subject of each of the licenses for each Issuing Authority and the range of activities to
which each license now relates is expanding to embrace all aspects of digital commerce and
culture. In this new landscape of communication technology speed is everything and the
broadband cable network that AT&T will acquire represents the fastest Internet
connection available to consumers in Massachusetts. AT&T's broadband cable empire in
this state and around the nation will permit AT&T to constrain this new medium as it
constrained growth and innovation on the telephone network prior to government action that
broke up AT&T's telephone monopoly. It has been on an open telephone network that the
Internet has grown.
AT&T is rapidly establishing a national broadband network for Internet connection.
If AT&T is permitted to maintain unfettered power to discriminate among providers, it
will alter for virtually every consumer the open "end to end" architecture of
the Internet. The Internet has thrived on "open access" to date. Permitting
AT&T to alter that landscape by bundling its own ISP as mandatory service and
discriminating against other, non-affiliated providers that seek access to the cable
pipeline will inevitably stifle competition and innovation.
Because there are genuine issues of fact and law that the Division can only decide
after a full evidentiary hearing and additional briefing, and because the issue of open
access to the Appellees' cable broadband network is of extraordinary importance to the
Issuing Authorities, consumers and providers throughout the Commonwealth, and to the
Internet community at large, the Division cannot render a decision in these matters simply
by laying hands upon the record developed in the public hearings and reliance upon the
summary disposition papers. In all events, the law cited herein and the record in each
case demonstrate that the Issuing Authorities' decisions to deny or conditionally approve
AT&T's FCC Form 394 transfer requests were reasonable and appropriate on the facts and
under applicable legal standards. Accordingly, as more fully set forth below, the Division
should deny the Appellees' motions for summary disposition in each case and hear evidence
and argument with respect to the propriety of the Issuing Authorities' decisions.
Procedural Background of the Cases
This matter involves the independent determination of the Issuing Authorities to deny
or to conditionally grant AT&T's FCC Form 394 requests to transfer the cable
television license of each Issuing Authority in connection with AT&T's acquisition of
MediaOne and MediaOne's various subsidiary companies.
A. The MediaOne/AT&T Merger and Application for Change in Control
On or about July 13, 1999, AT&T simultaneously filed an application for approval of
a change in control (FCC Form 394, with exhibits) with the 175 cities and towns in
Massachusetts that have granted cable television licenses to MediaOne. Under federal and
state law, as well as under the individual franchise agreements, the Issuing Authorities
determine after a hearing whether the proposed transfer should be approved. Applicable
regulations of the Division would have required all 175 towns to conduct hearings with
respect to the transfer of the subject cable licenses within sixty days of AT&T's July
13, 1999 filing. In response to these unique circumstances, the Division agreed, to
AT&T/MediaOne's request to conduct optional regional hearings throughout the
Commonwealth for the benefit of the subject cities and towns.
B. Regional Hearings
The Division informed all 175 communities that the Division had granted the request of
AT&T/MediaOne for regional hearings and that such hearings were being scheduled. The
Division informed each community that the Division would hold eleven regional hearings and
further informed the communities that each issuing authority, including those who
participate in the regional hearings, must ultimately consider the application and make a
decision on whether to approve the transfer on its own. See Cable Division Transfer
Bulletin 99-4 (June 28, 199) attached as Exhibit A.
The Division appointed Charles J. Beard as the Special Magistrate for the eleven
regional hearings. Following the completion of the regional hearings, Magistrate Beard
issued a twenty page Summary of Proceedings and Magistrate's Report dated September 24,
1999 (the "Magistrate's Report") containing a set of non-binding findings
and recommendations on issues that the Division had specified in the June 28, 1999
Transfer Bulletin. See Magistrate's Report at 1, attached as Exhibit B.
Magistrate Beard considered the scope of his charge to be focused on a narrow
interpretation of the four criteria set forth in 207 CMR 4.04 the consideration of the
transferee's (a) management experience; (b) technical expertise; (c) financial capability;
and (d) legal ability to operate a cable system under the existing license. See
Magistrate's Report at 2. It is important to note, however, that Magistrate Beard
acknowledged that this narrow interpretation was based upon Division regulations and
decisions that had yet to be challenged to any court in the Commonwealth. See id.
Magistrate Beard firmly acknowledged the importance of what he characterized as
"public policy" issues in the context of the transfer of MediaOne's cable
television monopoly to AT&T. The Magistrate's Report states, in pertinent part:
It is clear from the record in this proceeding that the transfer of MediaOne's licenses
to AT&T is an event far different from the hundreds, if not thousands, of license
transfers that have taken place to date in the Commonwealth. Never before has a company as
large and as diversified as AT&T, and with so many plans for transforming the delivery
of cable services, sought to enter the Massachusetts cable market.
The transfer obviously raises a host of public policy questions. I was charged with the
duty of helping cities and towns assess whether AT&T has the legal ability, the
management experience, the technical expertise, and the financial capability to fulfill
all of the obligations under the MediaOne licenses.
See Magistrate's Report at page 20. Foremost among these "public policy"
issues was the open access debate. Magistrate Beard noted that "the [open access]
issue has enormous importance as a public policy issue . . . " Id. In fact,
detailed testimony on the open access issue was presented at several of the regional
hearings and was summarized in the Magistrate's Report.
In the end, while Magistrate Beard perceived of his role and authority to make
recommendations following the regional hearings as limited in scope, the Magistrate made
note of the fact that the acquisition of cable monopolies in Massachusetts by AT&T is
an extraordinary event with vast public policy and other considerations and that the open
access issue is central among them. See id. at 3.
C. AT&T/MediaOne Presented Its Open Access Position In Public
Hearings
Despite a proposed limitation on the scope of the public hearings by Magistrate Beard,
it became obvious that the issue of open access was to play a major role in the
deliberations and considerations of each of the affected towns. See id. In
at least eight of the eleven hearings, residents and representatives of the various
issuing authorities raised the issue of open access. Throughout the hearings, the
participants at the hearings "raised important questions about whether the Road
Runner service [MediaOne's captive Internet service provider] is being provided in a
manner that will stifle competition and limit the growth of broadband services." See
id. (emphasis supplied).
Notwithstanding Magistrate Beard's belief that his scope of review was restricted in a
manner that precluded his consideration of the open access issue, the legal implications
of a closed system were specifically addressed at the hearings. Various issuing
authorities, consumer groups and other interested parties presented testimony that an
exclusive arrangement between AT&T and the MediaOne Road Runner service was
anti-competitive, including testimony that the arrangement was likely susceptible to
anti-trust challenge. See Weymouth Regional Hearing (September 9, 1999) at 67-68.
Further, AT&T's ongoing litigation in Portland, Oregon on the open access issue was
raised on numerous occasions, as were open access ordinances that had been enacted in
Broward County, Florida. See e.g. Barnstable Regional Hearing (August 9,
1999) at 55.
In addition, portions of AT&T's filing to the Canadian cable television authority,
the CRTC, regarding open access issues were read into the record. In that filing, AT&T
strongly advocated for an open access directive because of the anti-competitive impact of
a closed system:
[Cable operators and local telephone companies] have the ability to exercise
significant market power through the control which they exercise over bottleneck broadband
access facilities and through the dominance which they enjoy in their respective core
business markets
.
The potential for anti-competitive behavior can manifest itself in a number of ways.
One, pricing of Broadband accessing services below cost in some markets so as to preclude
service by other service providers. [Two,] [p]ricing services above costs in uncontested
markets thus providing [a source of profits] with which to subsidize other services.
Three, discriminatory behavior in relation to the terms and conditions for broadcast
access services and refusal to unbundle bottleneck components thus disadvantaging service
providers with whom the access provider competes in downstream markets.
In sum, there was important and extensive discussion in the hearings concerning the
anti-competitive effect of the planned transfer of control of the licenses despite
Magistrate Beard's view that the open access issue was not directly tied to the four
criteria in 207 CMR 4.04. AT&T participated actively in, and in certain instances
initiated, that debate.
There was also substantial discussion during the hearings concerning the adverse effect
of a closed system upon the public interest. As Magistrate Beard described, the
discussions were "frequently vigorous, sometimes contentious
and grew to the
point that AT&T decided to make a special presentation about its views on the
'open access' question." See Magistrate's Report at 4 (emphasis supplied).
AT&T not only presented its side of the open access debate at length in the ordinary
course of the hearings, see e.g. Foxboro Regional Hearing (September 2,
1999) at 59-66, but, in fact, introduced what it asserted as a panel of experts to make a
formal presentation on the issue. See Burlington Regional Hearing (September 8,
1999) at 90-127.
D. The Issuing Authorities' Hearings and Decisions
1. The City of Cambridge
On August 19, 1999, Cambridge, under the supervision of its City Manager, Robert Healy,
held a public hearing to address AT&T's transfer request as required by 207 CMR 4.00. See
Cambridge Hearing transcript attached as Exhibit D. At that time, Mr. Healy indicated that
the record would remain open for public comment until September 10, 1999. At the meeting,
Appellants presented their side of the debate concerning the issue of "open
access." The parties' also discussed the failure of MediaOne to comply with the
License Agreement.
As City Manager, it was the responsibility of Mr. Healy to decide whether to grant the
transfer request. Mr. Healy properly considered the information received from the meeting.
In addition, Mr. Healy made no decision prior to the close of the public hearing comment
period.
In his role as City Manager, Mr. Healy determined that any approval of the request must
be conditioned on several factors, i.e. compliance with the License, a showing of the
requisite management experience by AT&T, as well as non-discriminatory access to its
broadband system provided to other ISPs by AT&T. With respect to the latter, Mr. Healy
continued negotiations with AT&T beyond the public comment period, including
correspondence to AT&T consistently maintaining that approval of the request would in
part require this open access commitment from AT&T. See October 20, 1999 Healy
correspondence attached as composite Exhibit E.
In its submission to the Division, AT&T mischaracterizes a subsequent City Council
hearing as a "cable hearing" and as part of this record. The City of Cambridge
held its appropriately noticed public hearing as required by law on August 19, and kept
the record open for public comment for three weeks thereafter. The City Council meeting
referenced by AT&T in its submission was merely a forum for the City Manager to update
the City Council on the status of the license transfer. The Issuing Authority properly
rendered its decision on November 10, 1999, after failing on a number of occasions to
receive adequate assurance that the transferee (a) would comply with the existing license,
(b) had sufficient management experience and (c) would provide access to other ISPs in a
non-discriminatory manner. Thus, Cambridge complied with all applicable law regarding the
transfer decision and procedures. See Cambridge Decision attached as composite E.
2. The City of Quincy
On or about November 10, 1999 the City of Quincy issued a written decision to the
Division with respect to AT&T's FCC Form 394 request (the "Quincy
Decision"). A copy of the Quincy Decision is attached hereto as Exhibit F.
The Quincy Decision specifies that Quincy approves of the transfer of its cable license
from MediaOne to AT&T based, in part, upon the recommendations set forth in the
Magistrate's Report and based further upon the specific representations and warranties
that AT&T and MediaOne made at the regional public hearings referenced above. In
addition, consistent with its reliance upon the Magistrate's Report and the Magistrate's
acknowledgment of the importance of the open access issue, Quincy made its approval of
AT&T's FCC Form 394 request expressly contingent upon AT&T, as holder of the
Quincy cable license, providing nondiscriminatory access to its cable system by any
requesting Internet service provider on "terms and conditions that are at least as
favorable as the terms and conditions provided to itself, to its affiliates, or to any
other person." See November 10, 1999 correspondence.
3. The Town of North Andover
On or about November 10, 1999, the Town of North Andover sent AT&T a copy of its
written decision with respect to AT&T's FCC Form 394 request (the "North Andover
Decision"). North Andover also provided a copy of the decision to the Division. A
copy of the North Andover Decision is attached hereto as composite Exhibit G.
Representatives of North Andover participated in the regional hearing that the Division
conducted on August 12, 1999 in Lowell. Based upon the representations and warranties that
AT&T and MediaOne made at that hearing, the transcript of the proceedings, additional
communications with MediaOne, and its own independent review of the facts, North Andover
approved the transfer request of AT&T. North Andover's approval was expressly
contingent on five conditions: (1) that there be no increase in subscriber rates as a
result of the transfer of control; (2) that AT&T comply in all respects
with all of the terms and conditions of the North Andover Renewal License; (3) that
AT&T
resolve certain compliance matters with the Renewal License identified in an attachment
to the North Andover Decision; (4) that AT&T provide nondiscriminatory access to its
cable modem platform in North Andover for unaffiliated providers of internet and
"on-line" services; and (5) that AT&T pay all applicable taxes due to the
town.
4. The City of Somerville
On or about November 10, 1999 the City of Somerville issued a written decision to
AT&T with respect to AT&T's FCC Form 394 request (the "Somerville
Decision"). A copy of the Somerville Decision was provided to the Division. A copy of
the Somerville Decision is attached hereto as composite Exhibit H.
Representatives of Somerville participated in the region public hearing that the
Division held in Malden, Massachusetts. In addition to considering evidence and material
submitted at the Malden regional hearing, MediaOne wrote directly to Somerville with
respect to the issue of open access to Internet service providers over cable television
lines. Thus, MediaOne raised and responded to Somerville's concerns with respect to the
open access issue directly.
Somerville denied AT&T's transfer request. See Somerville Denial Letter
dated November 10, 1999 attached as Exhibit H. Among the reasons set forth in the
Somerville Decision are the following:
- In Somerville's review of the available evidence, AT&T, as the transferee, lacks
cable television management experience and technical expertise. Somerville concluded that
because AT&T, as transferee, had no direct experience in operating cable
systems for municipalities, the transfer was inappropriate.
- Somerville rejected AT&T's plea that it would obtain or gain an appropriate level of
municipal cable television experience by employing or otherwise relying upon MediaOne
employees. Somerville informed AT&T that MediaOne had not demonstrated management or
technical expertise with respect to the Somerville cable system that was beneficial to
Somerville's cable subscribers. Accordingly, AT&T's purported reliance on MediaOne's
experience and technical ability was rejected with sound reason.
Finally, Somerville noted that AT&T's refusal to permit nondiscriminatory access to
its high speed cable modem Internet platform poses a substantial legal barrier to the
operation of a free and competitive market for high speed data services. Somerville
specifically found that AT&T's position on this important public policy issue rose to
the level of a potentially actionable anti-trust violation that Somerville could not and
would not condone.
E. AT&T / MediaOne's Appeals
The Appellants filed appeals of the North Andover and Quincy Decisions on November 23,
1999. The Appellants filed their appeal in the Cambridge matter on November 29, 1999.
Lastly, Appellants filed their appeal of the Somerville Decision on December 3, 1999. The
Issuing Authorities filed motions for extensions of time in which to respond to the
Appellants' motions for summary decision and related materials on or about December 1,
1999, seeking an extension of time for filing responsive briefs and materials through
December 10, 1999. The Appellents assented to the requested extension and related motion.
The Issuing Authorities have also moved that the Division consolidate any hearings in
the above captioned matters in a single hearing or proceeding given the common issues of
law and fact in each case. Finally, the Issuing Authorities have opposed the Appellee's
motions for expedited proceedings in a separate memorandum filed contemporaneously with
this Opposition.
The Open Access Issue Is Central To These Appeals
A. Open Access on Broadband - This is the Way
Open access, simply described, is the requirement that cable companies offer
non-affiliated Internet Service Providers ("ISPs") non-discriminatory access to
broadband cable customers. Recently, cable television companies have begun to introduce
cable modem services that provide access to the Internet without a telephone connection
and at speeds many times faster than traditional telephone Internet connections. Cable
companies to date, however, have not permitted their own customers to select the
customer's preferred ISP. Rather than affording consumers "open access," cable
companies such as MediaOne and AT&T are requiring their customers to take the Internet
service that the cable company offers as a "bundled" or "tied"
service.
A customer in Massachusetts who wants broadband service cannot receive this desired
connection to the Internet without paying for the captive Road Runner ISP that MediaOne
owns and controls as a separate affiliated company. Thus, the MediaOne/AT&T system is
a "closed access" system in which any consumer who wants the benefits of cable
broadband data transmission must pay twice - first paying for the content,
navigation, email service and other services of the ISP that the cable company owns or
controls and then paying additional amounts for the customer's desired ISP. The results of
a "closed access" system on competition include higher prices, less consumer
choice, stifled innovation, and constraints on the free flow of information and electronic
commerce.
B. The Importance Of Open Access In The Current Cable Debate
The open access issue is being debated and, due to AT&T's refusal to consent to
true open access, litigated around the country. The Appellants describe the open access
debate as "trench warfare." In reality, AT&T has undertaken a nation-wide
blitzkrieg to kill the open access debate before it more seriously threatens AT&T's
emerging monopoly on the delivery of high speed Internet service and cable based telephone
service through AT&T's rapid purchase of cable operators around the country.
AT&T's recent public embrace of open access is grossly insufficient. Absent a legally
binding commitment, AT&T's open access announcement is a Trojan horse and makes all
the more reasonable the Issuing Authorities' refusal to open their gates to AT&T. As a
result, Massachusetts is in a unique position to shape this critical consumer and business
issue. The implications of AT&T's refusal to commit to open access will negatively
impact millions of Massachusetts consumers and hundreds of Massachusetts Internet service
providers and related businesses.
The issue of open access is not merely in the profit interest of giant ISPs like AOL
and Mindspring, but also in the public interest of the Internet community at large.
Nationally, proponents of open access include the following: the National Association of
Counties; Center for Media Education; Consumer Federation of America; Consumers Union;
Media Access Project; OMB Watch; and the OpenNET Coalition, consisting of more than 900
independent ISP and technology companies. We add the voices of Cambridge, North Andover,
Quincy and Somerville to the list.
More than 2.5 million people in approximately 42.1% of Massachusetts households are
"online." There are approximately 55 independent ISPs located in Massachusetts
and another 400 ISPs located outside the Commonwealth that provide services to
Massachusetts homes and residents. Internet service providers and related companies
provide tens of thousands of jobs to Massachusetts residents.
It is simply not credible to suggest that the open access issue - so fundamental to the
future delivery of Internet services in this state - is not relevant in this proceeding.
C. Denial of Open Access Is Harmful to Robust Competition
Limitation on consumers' ability to choose their ISPs means less competition among all
ISPs, slower growth and less innovation on the Internet itself. Without the robust
competition that open access provides, cable companies such as AT&T/MediaOne may exert
extraordinary control over content and access. Accordingly, the open access issue is a
legitimate public policy consideration for local authorities. As set forth below, the
authority to review issues of competition in the context of the transfer of a cable
license was delegated to local authorities by the federal government.
Efforts by entrenched cable companies and the emerging Internet giant, AT&T, to
characterize the open access debate as an effort to regulate the Internet should be
dismissed as what they are: a smokescreen generated to obscure the anti-competitive
conduct from which AT&T seeks to reap huge rewards. The debate is neither about
regulation of the Internet nor about denying cable companies a return on their investment.
"Open access" does not mean "free access." The Issuing Authorities
simply ask for a level playing field on which ISPs can compete by receiving access to
broadband cable networks on terms that are no more or less favorable than the terms that
cable companies offer to their own affiliated ISPs.
D. The Portland Litigation
The open access issue has already been litigated in favor of local authorities and open
access. Earlier this year, the United States District Court for the District of Oregon
ruled that an open access requirement imposed on AT&T by the City of Portland was
within the authority of the local government, not preempted by federal statutes that
regulate cable television, did not violate the First Amendment, Commerce Clause or
Contract Clause of the U.S. Constitution, did not violate the Oregon Constitution and did
not breach existing franchise agreements. See AT&T, et. al. v. City of
Portland, 43 F. Supp. 2d 1146 (D. Or. 1999), appeal pending, No. 99-35609 (9th Cir.)
(attached as Exhibit I) Against the backdrop of the Portland litigation, the Appellants
cannot credibly maintain that open access is not relevant or that it is not an issue that
local authorities may consider.
E. AT&T's Recent Commitment To "Open Access"
1. AT&T's December 6 Promise to the FCC
On December 6, 1999 AT&T wrote to FCC Chairman, William E. Kennard, purporting to
articulate AT&T's commitment to provide open access to unaffiliated ISPs at some point
in the future. The letter was the by-product of meetings between AT&T, Mindspring,
Excite@Home, a local official, the Media Access Project (a public interest group), and the
Mayor of Atlanta. Media Access Project dropped out of the discussion due to numerous,
fundamental problems with AT&T's position, nor did the Mayor of Atlanta join in the
letter. A copy of the AT&T letter of December 6 and responsive letters from MindSpring
and the Media Access Project of the same date are attached hereto as composite Exhibit J.
AT&T's promise to the FCC that AT&T will provide its own version of "open
access" to ISPs in or about mid-2002 is vaguely articulated in the December 6, 1999
letter which provides:
- a choice of ISPs;
- the ability to exercise a choice of ISPs without having to subscribe to any other ISPs
service (i.e. paying for MediaOne's captive Road Runner ISP and the consumer's ISP
of choice);
- a choice of Internet connections at different speeds and prices;
- control over "start pages" and other aspects of the consumer's Internet
experience;
- functions on the high speed modem that are, to the extent technically feasible,
comparable to those available on other high speed connections.
AT&T promised to negotiate open access contracts with independent ISPs "to
take effect upon the expiration of existing exclusive contractual arrangements . . .
" AT&T further stated that it would provide independent ISPs with:
- Internet transport services for high speed access at "reasonably comparable"
prices to those offered to other ISPs for similar services;
- the opportunity to market directly to consumers using AT&T's Internet broadband
network;
- the opportunity to bill customers directly;
- the opportunity to differentiate service offerings to consumers.
2. "Open Access Lite"
The AT&T commitment to the FCC is an important step in the right direction and an
admission by AT&T that open access is the means by which the Internet may best
continue to develop. However, at its core, AT&T does not promise true open access but
"open access lite" - a version of open access that AT&T is attempting to
control on AT&T's terms and on a timeline that permits AT&T to maintain the status
quo for more than two years.
As set forth in the letters of Dave Baker of MindSpring and Andrew Jay Schwartzman of
Media Access Project, AT&T's promise to the FCC does not commit AT&T to a truly
"open" path on its broadband network for independent ISPs. As noted by Mr.
Baker,
While we sincerely appreciate the open access commitments which AT&T is making,
they will not take effect until after the exclusive arrangements with affiliated companies
such as Excite@Home expire, currently set for mid-2002
Also, while this letter of
intent establishes an important principle that AT&T will not discriminate in favor of
affiliated ISP's like Excite@Home over unaffiliated ISP's, they could still impose
constraints such as limitations on video streaming or IP telephony on all users of their
system.
Baker correspondence, December 6, 1999 attached as composite Exhibit J.
AT&T's December 6 letter to the FCC is an effort to manage the advent of "open
access." AT&T's unsuccessful litigation in Portland and the continuing challenges
to steadfast defense of "closed access" at state and local levels are the
handwriting on the wall that motivated AT&T to abandon many of the first line defenses
that AT&T raised in the various public hearings at issue in this matter. Now that
AT&T is in apparent retreat from its anti-open access position, the Division should
consider the open access issue in a full evidentiary hearing on the merits of the Issuing
Authorities' respective decisions and respect their choice to make open access binding on
AT&T.
3. AT&T Should Not Be Permitted To Dictate the Timeline
As set forth in the correspondence attached hereto as composite Exhibit J, AT&T has
promised to transition its broadband Internet network to some form of open access
following the expiration of purported exclusive contracts with unidentified ISPs. As
stated in AT&T's December 6 letter to the FCC, ". . . AT&T has agreed to
adhere to the following [open access] principles once these exclusive contractual
arrangement no longer apply." The "exclusive contractual arrangements" to
which AT&T obliquely refers are its relationship with the nation-wide ISP Excite@Home
and, perhaps, to its contemplated ownership and control of the Road Runner ISP here in
Massachusetts.
According to AT&T, these alleged exclusive arrangements are scheduled to expire in
or about mid-2002. AT&T did not state in its letter to the FCC that AT&T owns 58%
of Excite@Home. Following the merger with MediaOne, AT&T would presumably own and
control the Road Runner ISP in Massachusetts. Therefore, AT&T's purported
"exclusive relationships" are essentially deals struck with itself. AT&T's
commitment to the FCC is an attempt to forestall the opening of AT&T's broadband
network for two years or more while AT&T develops new strategies to deal with the
public assault on its developing broadband monopoly. There can be little dispute that
AT&T can provide open access in short order without running afoul of the alleged
contracts it maintains with entities that it owns or controls. Permitting AT&T to
delay the opening of the broadband path to independent ISPs for two years or more would
allow AT&T to execute an "end run" around its own promise to remove the
barriers it has in place to nondiscriminatory broadband access.
Argument
A. The Summary Decision Standard Has Not Been Met
In this matter, the Appellants seek a summary decision from the Division that the
Issuing Authorities' denials or conditional approvals of the AT&T license transfer
were invalid under applicable law. Appellants fall far short of meeting their burden of
demonstrating that there are no issues of fact in this matter and that they are entitled
to judgment as a matter of law. The Appellants cite little or no authority for the
proposition that they are entitled to such a determination without hearing on the
important public policy issues that are central to this controversy. Appellants only
proffer 801 CMR 1.01(7)(h) as grounds for relief on a summary basis.
801 CMR 1.01(7)(h) simply provides the mechanism by which the Division may, in
appropriate circumstances, decide a case in a summary proceeding. The regulation does not
articulate the high standard that the Appellants must meet here to obtain relief without a
hearing. 801 CMR 1.01(7)(h) provides, in pertinent part:
[w]hen a party is of the opinion there is no genuine issue of fact relating to all or
part of a claim or defense and he is entitled to prevail as a matter of law, the Party may
move, with or without supporting affidavits, for summary decision on the claim or defense.
This regulation does not, in and of itself, entitle the Appellants to a summary
decision or establish the standard that Appellants must satisfy. It merely provides the
procedural mechanism for the motion.
As specifically set forth in Division Regulation 4.06, this appeal ". . . shall be
initiated in accordance with the provisions of M.G.L. c. 166A, §14." 207 CMR 4.06.
The Regulation goes on to specify that "[t]he Commission may, after a hearing
conducted pursuant to M.G.L. c. 166A, §14, issue such order as it deems appropriate .
. ." Id. (emphasis supplied). Thus, the need for a hearing on any appeal from
a transfer proceeding is presumed in the applicable regulation.
Chapter 166A provides that the Division ". . . shall hold a hearing upon
each such appeal, requiring due notice to be given to all interested parties." M.G.L.
c. 166A, §14. Again, the need for a hearing is presumed with the use of mandatory, rather
than permissive, language. The Appellants further rely upon the Division's decisions in Belmont
Cable Associates v. Board of Selectmen of the Town of Belmont, CATV Docket No. A-65
(1988) and Ridge Cablevision Corp. v. Board of Selectmen of the Town of
Braintree, CATV Docket No. A-33 (1983). In both cases, the Division articulated a
standard for summary decisions under 801 CMR 1.01(7)(h) that is virtually identical to the
standard for summary judgment under the Massachusetts and Federal Rules of Civil
Procedure.
In the Braintree case, the Division noted:
The [Division] has held that a summary decision is "appropriate where it has been
demonstrated that no genuine issue as to any material fact exists and where the moving
party is entitled to judgement as a matter of law."
CATV Docket No. A-33 at 2.
In the Belmont case, the Division noted:
Under 801 CMR 1.01(7)(f) [now (h)], 'any Party may with or without supporting
affidavits move for summary decision in his[/her] favor . . . The [Division] has held that
summary decision is 'appropriate where it has been demonstrated that no genuine issue [of]
material fact exists and where the moving party is entitled to judgment as a matter of
law.' (citation omitted). On a motion for summary decision, the moving party has the
burden of establishing that there are no issues of fact. Under Federal Rules of Civil
Procedure, all doubts are resolved against the moving party, and supporting affidavits and
depositions are carefully scrutinized by the court. (citation omitted).
CATV Docket No. A-65 at 3.
Accordingly, the Division has adopted a standard for motions made under 801 CMR
1.01(7)(h) that mirrors the summary judgment standard under the Massachusetts and Federal
Rules of Civil Procedure. The standard for summary decisions under M.G.L. c. 30A sets an
even higher bar.
Chapter 166A specifies further that any hearing provided for in Section 14 of the
statute ". . . shall be subject to the provisions of chapter thirty A." M.G.L.
c. 166A, §19. In the context of adjudicatory administrative proceedings under Chapter
30A, the standard for summary decisions is extraordinarily high - arguably higher than the
standard for summary judgment in civil litigation before a court in the Commonwealth.
In Massachusetts Outdoor Advertising Council v. Outdoor Advertising Board, 9
Mass. App. Ct. 775 (1980), the Massachusetts Appeals Court articulated a detailed standard
for summary decision in administrative adjudicatory proceedings. In ruling that a summary
decision was appropriate on the unique facts of that case, the Appeals Court held:
. . . in the State context before us, administrative summary judgment procedures do not
transgress statutory or constitutional rights to a hearing where those procedures are such
that they allow the agency to dispense with a hearing only when the papers or pleadings
filed conclusively show on their face that the hearing can serve no useful purpose,
because a hearing could not affect the decision.
Id. at 785-86 (emphasis supplied).
In the Outdoor Advertising case, the parties' submissions confirmed that there
were no facts in dispute and that the application of the governing law to those facts was
clear. Here, the landscape is quite different and has been radically changed in the past
few days by AT&T's purported promise to the FCC that AT&T will permit open access
on its cable networks. There are numerous facts in dispute with respect to AT&T's
merger with MediaOne, most notably its impact on competition and consumer choice,
AT&T's ability to provide nondiscriminatory access to its broadband network to
Internet service providers, how rapidly such open access service can be provided, and a
host of other pertinent facts. Moreover, the application of the statutes, regulations and
other authorities to the facts of this case is complex and a matter on which the Division
must hear evidence and argument from all interested parties, including any interested
parties who seek to intervene pursuant to 801 CMR 1.01(9) prior to the scheduled dates for
any hearings in this matter.
Outdoor Advertising clarifies the standard applicable here. In order to obtain
the relief they seek without the hearing that the Division's regulations and Chapter 166A
require, the Appellants must demonstrate on the face of the submissions that there
is absolutely no possible useful purpose to a Division hearing. Thus, the high standard
that governs summary decisions in the context of an administrative proceeding is more akin
to a motion to dismiss as opposed to a motion for summary judgment. If there is any
possibility that a hearing on the merits of the case will be "useful," the
Division must conduct an evidentiary hearing.
Even if the lower "summary judgment" standard applies, Appellants are not
entitled to relief without a hearing. In this case, the Division cannot take action
without providing the Issuing Authorities, or other interested parties, the opportunity to
be heard and to put the evidence in support of the Issuing Authorities' respective
decisions before the Division and in the record of this case.
For the reasons described above, the Appellants have failed to meet the high standard
for a summary decision and the Division should deny the motion for summary disposition.
Moreover, as set forth below, Appellants legal arguments fail as well.
B. Application of the Regulations to Exclude Consideration of
Open Access Exceeds the Division's Authority
Appellants maintain that the Division's regulations preclude any consideration of
the open access issue by the Issuing Authorities. If the Division interprets Regulation
4.04 so as to prohibit consideration by the Issuing Authorities of the anti-competitive
effects of closed access, then the Regulation as applied must be found invalid. The
Division will have exceeded the authority granted it by statute and impermissibly narrowed
the rights of the Issuing Authorities in a manner contrary to the express intent of the
relevant federal legislation and its own enabling statute. As noted earlier, these
Regulations have yet to be challenged; therefore, this is a critical matter of first
impression that must be carefully addressed by the Division. See Magistrate's
Report at 2.
1. If applied to preclude consideration of open access, the
regulations as applied are contrary to Congressional intent and federal law
Congress gave express authorization for consideration of competition issues during
transfer proceedings. 47 U.S.C. §533 provides in relevant part,
Nothing in this section shall be construed to prevent any state or franchising
authority from prohibiting the ownership or control of a cable system
in
circumstances in which the state or franchising authority determines that the acquisition
of such a cable system may eliminate or reduce competition in the delivery of cable
service in such jurisdiction.
47 U.S.C. §533(d)(2) (emphasis supplied).
This provision of the Cable Television Consumer Protection and Competition Act of 1992
amended prior legislation in order to promote competition in cable services. See
H.R. Rep. No. 102-628 at 91 attached as Exhibit K. Congress explicitly gave the states or
franchising authorities the power, and thus the responsibility, to make license control
decisions in a manner intended to promote or maintain competition. See id.
See also Portland, 43 F. Supp. 2d at 1152.
Prior to the 1992 amendment, the legislation generally prohibited a franchising
authority from denying control of a franchise license because of an applicant's ownership
or control of any other media interests. See 47 U.S.C. 533(d). Reading this
restriction as absolute, the court in Cable Alabama Corp. v. City of Huntsville
held that the city could not deny a license transfer because of adverse effects the change
in control would have on competition within the city. See 768 F. Supp. 1484 (N.D.
Ala. 1991). Reacting to this interpretation, Congress amended the legislation to
explicitly grant this authority. See H.R. Rep. No. 102-628 at 91. As provided in
the legislative history,
[The Cable Alabama] ruling clearly is inconsistent with the intent of [§533] (c) and
(d). Moreover, it is inconsistent with one of the major purposes of the Cable Act, which
is to "promote competition in cable communications,"
. The amendment to
subsection [533] (d) clarifies the right of the franchising authorities to promote
competition by denying a franchise to a person if the grant of the franchise would limit
competitive cable services in a franchise area. The amendment
also overturns the
decision in Cable Alabama Corp." See id.
Thus, a local franchising authority was expressly provided the right to promote
competition by denying a license transfer if such a transfer would limit competitive cable
services in the authority's jurisdiction.
This designation of power to the local franchising authorities by the federal
government is entirely consistent with cable regulation historically. From its first foray
into cable regulation now fifteen years past, Congress maintained that the local
franchising process was to be relied upon as "the primary means of cable television
regulation." See Cable Communications Policy Act; H.R. Rep. No. 98-934 at 19
attached as Exhibit L. This reliance was a continuation of the local authority that had
been exercised for decades over cable operators pursuant to the general police powers over
the streets and public ways accessed by the systems.
In addition, subsequent legislation directed at cable services expressly preserved the
state and local authority's ability to counter practices intended to restrain commerce. See
47 U.S.C. §521 note; 47 U.S.C. §152 note (c)(1). In 1992, Congress stated that its
actions were in no way to be construed "to alter or restrict in any manner the
applicability of any Federal or State anti-trust law." 47 U.S.C. §521 note. Later,
Congress noted that the Telecommunication Act of 1996 "shall not be construed to
modify, impair or supersede Federal, State, or local law unless expressly so provided in
such Act or amendments." 47 U.S.C. §152 note (c)(1). Thus, the obligation of the
local authority or state to maintain and promote competition delegated by 47 U.S.C. §533
is a consistent application of federal policy.
Congress's intent to use the franchising authority as the primary means of preserving
competition and protecting the public interest is further evidenced by 47 U.S.C §552(c).
This provision explicitly provides, "[n]othing in this subchapter shall be construed
to prohibit any State or any franchising authority from enacting or enforcing any consumer
protection law, to the extent not inconsistent with this subchapter."
Massachusetts clearly did not intend to exercise this right to protect competition and
consumer choice at the state level. The Massachusetts Legislature expressly determined
that all authority to approve transfers was to be vested in the issuing authorities
subject only to the limitation that a transfer decision not be "arbitrary or
unreasonable." See M.G.L. c. 166A, §7. As a result, the federally granted
authority to promote competition and protect consumer choice rests with the issuing
authority. A decision by the Division to deny the local authority this power, thereby
precluding consideration of the anti-competitive effects of this transfer, is inconsistent
with federal law and must be found invalid.
2. The regulations as applied are inconsistent with the purposes of G.L. c. 166A
The refusal to allow consideration of the issue of open access by the Division is also
contrary to the intent of the Massachusetts Legislature and the Division's enabling act.
General Law 166A, §7 requires an issuing authority to review any application for a
license transfer and provides that consent thereto, "shall not be arbitrarily or
unreasonably withheld." The Division's strict application of Regulation 4.04 as
advocated by Appellants would narrow the Issuing Authority's discretion so as to preclude
consideration of a factor significant to a municipal cable license transfer. 207 CMR 4.04.
Such a restriction cannot be reconciled with the purpose of the governing legislation and
cannot stand. See Nuclear Metals, Inc. v. Low-Level Radioactive Waste Mgt. Bd.,
421 Mass. 196, 211 (1995).
An administrative agency has no authority to exceed the power conferred upon it by its
enabling statute. See Massachusetts Hospital Assoc. v. Dept. of Medical Security,
412 Mass. 340, 346 (1992) (statute did not empower department to set performance standards
for hospital collection and credit collection practices). It is well established that an
agency's rulemaking power does not include the power to make law. See Loffredo
v. Center for Addictive Behaviors, 426 Mass. 541, 545 (1998) (agency lacked authority
to create private right of action when intent for such not expressed in statute). Instead,
an agency maintains the much more limited power to carry into effect the purposes of the
legislature as expressed by statute. See id. Thus, agency action must be
invalidated when it is not consonant with the purpose of the statute. See Nuclear
Metals, 412 Mass. at 211.
The Massachusetts Legislature recognized the need for a town or city to maintain
control over its cable license in order to protect its residents and, by statute, granted
it wide discretion suitable for such supervision. See M.G.L. c. 166A, §7; see
also Campbell CATV Systems Assoc. Part III v. East Bridgewater, Docket No.
A-46 (CATV 1984) (to allow Commissioner's opinion regarding applicant's corporate
structure as evidence that denial of license grant is unjustified would usurp the issuing
authority's role in the licensing process, as it maintains ultimate responsibility for
grant.). To this end, the Division has acknowledged that the "arbitrary or
unreasonable" standard of review parallels the "arbitrary or capricious"
review of transfer decisions in other areas of the law. See Rollins Cablevision
v. Somerset, Docket A-64 (1988).
Under the arbitrary or capricious standard, deference should be given to the
considerable expertise and interest of a local licensing authority and its judgment should
not be disregarded unless deemed whimsical or not based on logical analysis. See Great
Atlantic & Pacific Tea Co. v. Bd. of License Comm. of Springfield, 387 Mass. 833,
837-38 (1983) (recognizing degree of expertise of local authority in alcoholic beverage
regulation); Cf. McDonald's Corp. v. East Longmeadow, 24 Mass. App. Ct. 904,
905-06 (local authority permitted to look at factors not directly connected to food
preparation and delivery in denying food license); Mosey Café, Inc. v. Licensing Bd.
for City of Boston, 338 Mass. 199, 205 (1958) (statute without standards for granting
entertainment licenses confers quasi-judicial authority to do so in a manner that is not
unreasonable or arbitrary).
Regulation 4.04 purports to restrict the issuing authority's consideration of a license
transfer to only four factors deemed germane by the Division. Such a restriction is
entirely at odds with the Massachusetts Legislature's intent if, as here, a relevant and
reasonable concern cannot be addressed as a result. See Nuclear Metals, Inc.,
421 Mass. at 211. Application of Regulation 4.04 to prevent the Issuing Authorities from
considering the issue of open access in this transfer decision clearly exceeds the
Division's mandate to carry into effect the purposes of the statute and instead
constitutes unauthorized lawmaking. See Loffredo, 426 Mass. at 545. Imposing
these limits impermissibly narrows the ample discretion granted the Issuing Authorities
pursuant c. 166A, §7 and cannot survive scrutiny. See Mass. Hospital Assoc.,
412 Mass. at 346. Due to the serious competition implications of AT&T's closed access
policy and its sudden conversion into an open access advocate, the requirement that open
access be provided to customers is certainly not arbitrary or unreasonable and therefore
must withstand Division review.
C. The Division Should Waive Regulation 4.04 For Consideration
Of Open Access In The Transfer Decision
The Division could easily avoid invalidation of its own regulations in this unique
circumstance by waiving the application of Regulation 4.04. Doing so would be consistent
with the purpose of the waiver provision and the intent of both Congress and the
Massachusetts Legislature as described above. The Division should upon its own initiative,
and the Issuing Authorities hereby request the Division to, waive Regulation 4.04 for the
purposes of this appeal. In support of this request for waiver, the Issuing Authorities
submit the information provided in the Magistrate's Report, the regional hearings, the
Cambridge hearings, and relevant correspondence.
1. The negative effects on competition of this transfer
justify the waiver of Regulation 4.04
The Division has the authority to waive particular provisions of the regulations when
doing so would be "consistent with the public interest." See 207 CMR
2.04; In Re Amendment of 207 CMR 4.01-4.06 at ¶61. In its own words, the Division
noted,
the [Division's] role must be flexible given the current trends of the
telecommunications industry. Trying to craft and interpret transfer regulations at a time
when technologies, corporate structures, and industries are changing and converging is
difficult. The [Division] has determined, therefore, that it is prudent to establish a
waiver provision in its transfer regulations. . . [to] allow the [Division] the necessary
flexibility to evaluate novel circumstances surrounding transfer proceedings.
In Re Amendment of 207 CMR 4.01-4.06 at ¶60.
To the extent that the promotion of competition required by the federal government is
not subsumed within the consideration of "legal ability," the open access issue
is of such relevance and importance that the Division must waive application of Regulation
4.04 on its own initiative.
Although Regulation 4.04 may serve its purpose for a majority of common license
transfers, this request by AT&T implicates public policy questions of "enormous
importance" that reach far beyond what a narrow interpretation of the Regulation can
properly address. See Magistrate's Report at 18. As AT&T's Canadian submission
underscores, the provision of open access is critical to removing a situation where
competition in a major market is unduly impaired. See AT&T Comments at i.
In enacting Regulation 4.04, the Division claims to have followed reasoning dating as
far back as 1983. See Bay Shore Cable, Docket No. A-55 citing CATV
Commission Advisory, March 9, 1983. In fact, Bay Shore Cable allowed consideration
of additional factors, including character and performance in other communities. In any
event, a narrow interpretation of the criteria enumerated in 4.04 does not accommodate
consideration of the extensive and damaging effect upon competition raised by the transfer
at hand. This is exactly the convergence of technology and industries for which the waiver
was enacted. Failure to exercise this waiver power is inconsistent with the Division's own
regulations and contrary to the powers expressly delegated by the federal government.
As the Special Magistrate noted, this transfer "is an event far different from the
hundreds, if not thousands of license transfers that have taken place to date in the
Commonwealth
. The transfer obviously raises a host of public policy
questions." See Magistrate's Report at 20. The Division must waive application
of Regulation 4.04 in order to confront these public policy questions. It should do so in
the transfer proceeding, so that the appropriate resolution is uniform, speedy, and
protective of the public interest.
2. AT&T received sufficient notice and opportunity to address the issue of open
access
Pursuant to Regulation 2.04, North Andover previously requested a waiver of Regulation
4.04 for its determination of the license transfer. 207 CMR 2.04. This request was denied
by the Division on the grounds that it was untimely and, based upon an erroneous
assumption, that the parties did not have adequate notice to respond at the regional
hearings to open access advocates. See Division correspondence dated September 23,
1999. attached as Exhibit M.
G.L. c. 30A, §11 requires that parties to a hearing be provided sufficient notice of
the issues so that they have "a reasonable opportunity to prepare and present
evidence and argument." M.G.L. c. 30A, §7; see also New England
Telephone & Telegraph Co. v. Dept. of Public Util., 372 Mass. 678, 686 (1977). In
practice, the notice must "sufficiently apprise" a party of the relevant issues.
See O'Brien v. Div. of Employment and Security, 393 Mass. 482, 484 (1984).
The record of the regional hearings and subsequent meetings between AT&T and the
Issuing Authorities demonstrate not only that AT&T and MediaOne were sufficiently
apprised, but took every advantage to present evidence and argument.
Unfortunately, the Division did not have the opportunity to review the Magistrate's
Report prior to denying North Andover's request for waiver. Examination of the Report
dispels any concerns the Division may have harbored that AT&T and MediaOne could not
sufficiently respond to the open access issue. To the contrary, "[t]here was
considerable discussion during the hearings about the issue of 'open access'."
Magistrate's Report at 17. From the time the issue was first raised on August 4, AT&T
had nine additional hearings and over a month to present its side of the debate. See
LaPointe v. License Bd. of Worcester, 389 Mass 454, 458 (1983) (insufficient notice
of hearing cured at first hearing and continuation for one week deemed sufficient).
Indeed, AT&T took full advantage of these opportunities. It spent significant time
and resources advocating its view, including introduction of a panel of experts to put its
views formally on record. See id. On another occasion, an AT&T employee
spoke at great length specifically concerning the legal and non-legal justifications for a
closed system. See Foxboro Regional Hearing at 59-66. According to the Magistrate,
"the discussions were frequently vigorous, sometimes contentious." Id. at
3. As evidenced by
the section of the report devoted strictly to the numerous competing arguments raised
during the hearings, the open access issue was extensively covered during the regional
hearings. See id. at 18-20. It is clear, then, that Appellants received
sufficient notice so that they could respond and completely address the issue of open
access in a meaningful manner. Moreover, AT&T sought and was granted numerous
additional opportunities to address local officials directly in meetings and written
communications.
The Cambridge hearing likewise provided AT&T a meaningful opportunity to present
its side of the open access argument. See Cambridge Hearing at 39-42, attached as
Exhibit D. In addition, Cambridge officials and Appellants met and exchanged
correspondence on a number of occasions during which the issue of open access was
discussed. See Exhibit E. This included a three page letter from AT&T to the
Cambridge City Manager exclusively directed at the issue of open access. See
November 3, 1999 correspondence.
D. Regulation 4.04 Substantially Impairs the Issuing
Authorities' Contractual Rights
Even if the Division finds generally that Regulation 4.04 should be applied in these
circumstances, specific application of these restriction to these license agreements is
impermissible because it would substantially impair the Issuing Authorities' contractual
rights in a manner unnecessary to serve an important public purpose. See U.S.
Const. Art. I, §10; Allied Structural Steel Co. v. Spannaus, 438 U.S. 234 (1978).
The Supreme Court has developed a three-step test to determine if subsequent
legislation has impermissibly impaired contractual rights. See Spannaus, 438
U.S. 234 (1978). First, the court must determine that a subsequent law has in fact
impaired a contractual relationship. See id. at 244; Parella v.
Retirement Bd. of R.I. Employee's Retirement System, 173 F.3d 46, 59 (1st Cir. 1999).
Second, it must then decide whether this impairment is substantial. See Spannaus,
438 U.S. at 244; Little v. Comm. of Health & Hospitals of Cambridge, 395 Mass.
535, 555 (1985). In making this determination, it should consider how a contract is
affected and whether the abridged right is "replaced by an arguably comparable
security provision." See United States Trust Co. of New York v. New Jersey,
431 U.S. 1, 19 (1977). Finally, the court must then determine if the substantial
impairment is reasonable and necessary to "meet an important general social
problem." See Spannaus, 438 U.S. at 247.
Application of Regulation 4.04 to the Cambridge, Somerville, and North Andover license
agreements violates the Contract Clause. First, a contractual relationship unquestionably
exists between the Issuing Authorities and MediaOne, and the Issuing Authorities'
contractual rights concerning the transfer approval process are restricted by Regulation
4.04. See Eagerton, 462 U.S. 174, 189 (1983) (state law prohibiting certain
tax allocations by company restricted contract options).
Moreover, these rights are substantially impaired by forcing the Issuing Authorities to
narrow their considerations as required by Regulation 4.04. Under its license agreement,
Cambridge expressly reserved the supervisory capacity to inquire into "whether the
proposed change of control and ownership is in the public interest." Cambridge
License, §2.2(d) attached as Exhibit N.
Likewise, both Somerville and North Andover by contract reserved the right to consider,
amongst other things, experience in the cable industry, character qualifications,
performance in other communities, and "other lawful and reasonable criteria in
accordance with applicable laws." North Andover License, §2.4(b) attached as Exhibit
O; Somerville License, §2.6(b) attached as Exhibit P (right to consider "any other
criteria allowable under law").
At the time the contracts were executed, an issuing authority in Massachusetts was
entitled to base its transfer decision on any concern as long as it was reasonable and not
arbitrary. See M.G.L. c. 166A, §7. Moreover, as discussed in detail above, federal
law explicitly authorized an issuing authority to deny a cable license transfer where such
a change in control would limit competition in the provision of cable services. See
47 U.S.C. §533(d)(2).
Application of Regulation 4.04 to preclude consideration of open access to the Licenses
abolishes the Issuing Authorities' contractual right to consider the effects of the
transfer upon consumer interests and fails to replace it with any comparable security
provision. See United States Trust, 431 U.S. at 19. This clearly constitutes
a substantial impairment of the license agreements. See Spannaus, 438 U.S. at 244.
Significantly, these restrictions do not confront an important social problem. See
id. at 247. On the contrary, eliminating their right to consider issues
characterized by Magistrate Beard as of "enormous importance" undermines the
Issuing Authorities' ability to protect the interests of their residents. See id.
at 249. In such circumstances, the deference granted the Division as to the necessity and
reasonableness of a particular measure "simply cannot stand." Spannaus,
438 U.S. at 247; Mass. Hospital Assoc., 412 Mass. at 345-46.
E. Regulation 4.04 Should Not Be Applied Retroactively
Even if the Division finds that application of Regulation 4.04 is not a violation of
the Contracts Clause, the Regulation and the restrictions imposed thereunder cannot be
applied retroactively to the Cambridge and Somerville license agreements. See Salem
v. Warner Amex Cable Communications, Inc. 392 Mass. 663 (1984). The license agreements
were executed before Regulation 4.04 or any regulation interpreting the relevant statute
was adopted, therefore the applicable law for this appeal must be whether consent to
AT&T's license transfer was arbitrarily or unreasonably withheld, especially in light
of their motive of preserving competition. See M.G.L. 166A, §7.
As a general rule, the law in existence at the time an agreement is executed
necessarily becomes part of the agreement, and amendments to the law after execution are
not incorporated unless the contract unequivocally demonstrates the parties' intent to so
incorporate. See Feakes v. Bozyczko, 373 Mass. 633, 636 (1977). In Salem,
the Supreme Judicial Court held that amended procedures for cable rate regulation did not
apply to a cable license signed two years prior because the license did not clearly
indicate that the parties intended to incorporate future amendments of the legislation and
regulations. See 392 Mass. at 667-69. The Court found the absence of the words
"and amendments thereto" in the license agreement as significant in determining
that there was no intent of the parties to incorporate future changes. See id.
at 667.
Regulation 4.04 unquestionably altered an issuing authority's scope of considerations
in a license transfer decision. First, Appellants assert that the Division's decision in Bay
Shore Cable TV Assoc. v. Weymouth effectively established Division policy prior to the
execution of the licenses. CATV Docket A-55 (1985). Appellees agree that the Division may,
in the interest of consistency, view prior adjudication as guiding. However, as the
Supreme Court pointed out, this is "far from saying
that commands, decisions,
or policies announced in adjudication are 'rules' in the sense that they must, without
more, be obeyed by the affected public." NLRB v. Wyman-Gordon, 394 U.S. 759,
765-66 (1969). Further weakening this position is the fact that Bay Shore Cable
allowed for considerations beyond the four enumerated in 4.04 and was decided only a month
prior to the execution of the Cambridge License, hardly the time necessary to establish
firm Division policy. CATV Docket No. A-55. Second, contrary to Appellants' assertion, the
Division in 1988 agreed that an issuing authority was permitted to review factors other
than management, technical expertise, financial capability and character so long as these
other considerations were not arbitrary or unreasonable. See Somerset,
Docket A-64 at 4-5, explaining Bay Shore Cable, Docket A-55. Thus, the
applicable law concerning the discretion of an issuing authority was substantively changed
in 1995 by the Commission Report and Order promulgating Regulation 4.04. See In
Re Amendment of 207 CMR 4.01-4.06 at 18.
There is no language in either the Cambridge or Somerville license that
"clearly establishes" the parties' intent to incorporate changes in the existing
law into their agreement. To the contrary, both licenses reiterate the standard of review
in effect at the time of the agreement, i.e. that consent shall not be unreasonably or
arbitrarily withheld. See Cambridge License §2.2(a); Somerville License §2.6(a).
Moreover, in the absence of defining standards, the parties emphasized particular factors
that would constitute appropriate considerations in a license transfer. See
Cambridge License §2.2(d); Somerville License §2.6(b). Thus, the alteration of the
substantive rights of the parties under these license agreements would be an unlawful
retroactive application of Regulation 4.04. See Salem, 392 Mass. at 668-69.
F. Conditional approval is an appropriate exercise of the
Issuing Authorities' pre-existing rights under the license agreements
The appellants represent the Issuing Authorities' conditional approval subject to open
access as an amendment to the licensing agreements. On the contrary, the Issuing
Authorities' consideration of open access is the legitimate exercise of a right reserved
under the agreements and applicable law.
As explained above, the applicable law authorizes the Issuing Authorities to deny a
request for license transfer where such a change in control would limit competition in the
provision of cable services. See 47 U.S.C. 533(d)(2); M.G.L. c. 166A, §7. This
power necessarily includes the "lesser power to impose conditions under which it will
permit a change in control." Portland, 43 F. Supp.2d at 1152. Thus, the
conditional approvals by Quincy and North Andover are an appropriate exercise of their
rights under the law and do not constitute any amendment of the licensing agreements.
G. Failure to Provide Open Access Involves Appellant's Legal
Ability and Technical Expertise to Operate the Cable System under the Existing License.
The Division need not find its own regulations invalid. Alternatively, the Division
could find that the Issuing Authorities' denials or conditional approvals of the transfer
application are based upon consideration of transferee's legal ability and technical
expertise to suitably operate the cable system under the existing licenses and must be
upheld.
1. AT&T's legal ability
a. The Issuing Authorities retain the power provided by
federal legislation to promote competition
The inability or unwillingness of AT&T to provide open access to its system is
contrary to the competition endorsed by Congress in this field. See 47 U.S.C.
§533. There exists a legitimate and reasonable concern regarding the adverse effect on
competition that this transfer would promote, a concern that Congress expressly recognized
as within the purview of an Issuing Authority's consideration in a transfer proceeding. See
47 U.S.C. §533(d)(2).
Congress not only recognized the importance of competition within the industry but
explicitly left it to the state or local issuing authority to ensure that this competition
existed. See id.; AT&T Corp. v. Portland, 43 F. Supp.2d 1146,
1152 (D.Or. 1999). Along these same lines, Congress also expressly granted the state or
local authority the power to act for the purpose of consumer protection in the sphere of
cable services. See 47 U.S.C. §552(c).
The Massachusetts Legislature chose not to assume the power to control competition at
the state level but instead limited the Division's power to deferential review of an
issuing authority's transfer decision. See M.G.L. c. 166A, §7. This allocation of
power placed the right and responsibility of maintaining competition squarely upon the
shoulders of the Issuing Authorities and any review by the Division must be limited to
consideration of whether the Issuing Authorities were arbitrary or unreasonable. See
Id.
b. AT&T's failure to provide open access adversely affects
competition and implicates restraint of trade provisions
AT&T's failure to provide open access clearly limits competition and consumer
choice in the provision of cable services. In addition, the Issuing Authorities are
reasonably concerned that this refusal implicates serious federal and state restraint of
trade policies. See 15 U.S.C. §§1-7; M.G.L. c. 93 §4.
AT&T has itself denounced the anti-competitive effects of a closed system and
trumpeted the need for regulation to ensure equal access for ISPs in a different venue. See
AT&T Canada's Comments to CRTC attached as Exhibit C. In its submission to the CRTC,
AT&T noted the ability of companies to exercise significant market power through the
control which they assert over "bottleneck broadband" (their words) access
facilities. See id. at i. This anti-competitive behavior was forecasted by
AT&T to manifest in a number of ways, including "discriminatory behaviour in
relation to the terms and conditions for broadcast access services and a refusal to
unbundle bottleneck components, thus disadvantaging service providers with whom the access
provider competes in downstream markets." Id. AT&T requested that the
Canadian government mandate open access until "safeguards to ensure that broadband
access services continue to remain available from the cable companies on a
non-discriminatory and unbundled basis." See id. at ii. It is difficult
for AT&T to now disclaim the anti-competitive effects of it operating a closed system
in Massachusetts.
Furthermore, it is a violation of both federal and state law to restrain trade or
commerce by creation of a "tying" or "bundling" arrangement. See
15 U.S.C. §1, M.G.L. c. 93 §4. Such an impermissible arrangement has four elements: (1)
two distinct and separate products; (2) a refusal to sell the tying product separate from
the tied product; (3) the seller's possession of sufficient economic power with respect to
the tying product to appreciably restrain free competition in the market for the tied
product, and for the purposes of the Sherman Act; and (4) a not insubstantial amount of
interstate commerce in the tied product affected by the tying arrangement. See Eastman
Kodak Co. v. Image Technical Servs., Inc., 504 U.S. 451, 461 (1992); Parikh v.
Franklin Medical Center, 940 F.Supp. 395 (D. Mass. 1996).
Here, AT&T will continue an arrangement whereby a Massachusetts consumer cannot
receive connection to the internet through AT&T's broadband cable system without
paying for the Road Runner ISP service that MediaOne controls as a separate, affiliated
company. Thus, a consumer desiring the full content and services of another ISP will be
forced to pay twice, once for the mandated Road Runner ISP and again for the desired ISP.
The obvious results of such bundling include higher costs, decreased consumer choice and
stifled innovation. It is clear that the refusal of AT&T to provide open access to
other ISPs implicates the necessary elements of this anti-trust provision.
There is recent precedent to support these denials and conditional approvals upon this
basis. In Portland, AT&T argued that the city's review of the transfer
application was limited to consideration the transferee's technical, legal and financial
qualifications. See 43 F.Supp.2d at 1155. The Portland court found that
mandatory access requirements were appropriately related to the transferee's legal
qualifications to assume control of the licenses so as to fall within the city's
contractual rights. See id.
The anti-competitive results impair AT&T's fundamental legal qualifications to
perform under the contract and are appropriate considerations by the Issuing Authorities
in the license transfer decision. They certainly are not arbitrary or unreasonable factors
on which to base a transfer application determination. Therefore, the decisions of the
Issuing Authorities must be upheld. See M.G.L. c. 166A, §7; Portland, 43
F.Supp.2d at 1155.
2. AT&T does not maintain or is unwilling to utilize the
technical expertise to perform this contract in a lawful manner.
The technology to operate the cable systems in a lawful manner is available to
AT&T. Connection of multiple ISPs to an existing cable carrier's facility has been
demonstrated on a smaller scale and this technology is essentially in existence for much
larger operations. One carrier successfully demonstrated the connection of multiple ISPs
in Clearwater, Florida. See Burlington Regional Hearing at 121, 145. In a separate
proceeding, the Canadian Radio-television and Telecommunications Commission (CRTC) noted
that a similar demonstration was being conducted within its jurisdiction. See CRTC
99-11 attached as Exhibit T.
At the regional hearings, AT&T acknowledged these successful multiple ISP
connections but asserted that multiple connections on a larger scale would require
"substantial operational effort," including investment in new functionality and
an upgrade of "a bunch of our existing hardware and software." See
Burlington Hearing Transcript at 122. The aforementioned CRTC decision belies this grim
outlook by AT&T. There, the Canadian Cable Television Association, a group of cable
providers currently offering high speed retail Internet services of comparable magnitude
as MediaOne, announced that it expects that cable companies will be in a position to
implement commercial access service as early as mid-2000. See CRTC 99-11. Most
contradictory, a Tacoma tele- communication company just announced that it will provide
open access to multiple ISPs through its cable system by the end of the year, as the
company's network has "worked flawlessly" in its tests using three separate
ISPs. See Press Release (December 1, 1999) attached as Exhibit U.
A representative of GTE, the carrier that performed the Florida demonstration, likewise
dispelled AT&T's claim that open access on a large scale is not readily feasible but
instead only required reasonable effort and commitment. See Burlington Regional
Hearing at 145; see also Weymouth Regional Hearing at 88 (MIT Professor
Hausman noted that required open access in Canada and Australia did not deter relevant
providers from the necessary investment and upgrade).
Finally, AT&T has fallen upon its own sword. Its recent agreement with the FCC
confirms the fact that it either presently maintains the technology to provide for open
access or is in a position to apply this technology shortly. The President of the Media
Access Project, in his letter explaining why he could not sign off on AT&T's open
access declaration, stated:
Even as technologists at the highest levels of AT&T and Excite@Home were
representing to me that there is no technological impediment to providing citizens with
access to multiple ISP's, their lobbyists have continued to argue the contrary position
before numerous state and local legislative and regulatory bodies. Indeed a significant
factor in my decision to withdraw from the talks you asked me to attend was the claim
by Excite@Home's General Counsel that "The technology simply does not yet
exist to allow multiple ISPs to share a coaxial cable on a commercial basis."
See Schwartzmann correspondence at composite Exhibit J.
The statements made by AT&T throughout the regional hearings and Cambridge hearing
to the effect that such application would not be economically or technologically feasible
for a considerable amount of time is characteristic of the general insincerity with which
AT&T has addressed the legitimate concerns that the Issuing Authorities have raised
throughout these transfer proceedings.
It is clear that AT&T, by the intransigence it continues to display on this matter,
is unwilling to effect the technical capacity necessary to operate and update the cable
system as required under applicable law, and the existing licenses. The Issuing
Authorities did, and indeed must, account for this refusal in their review of the transfer
application. The failure of the transferee to utilize the available technical expertise to
operate the cable systems in a lawful manner is sufficient grounds for denying a license
transfer and the Issuing Authorities' decisions must be upheld on these grounds.
3. Cambridge's denial based upon the additional consideration
of the transferee's lack of management experience and failure to adhere to the existing
license is appropriate grounds for denying AT&T's transfer request.
The Cambridge Denial of AT&T's transfer request was appropriately based upon a
number of additional factors. AT&T's attempt to mischaracterize the Cambridge
proceedings and ultimate basis for its decision must be addressed. First and foremost,
Appellants assert that they "presented evidence satisfying the four relevant criteria
set forth in 207 CMR §4.00." See Appellants' Memorandum at 10. Despite this
portrayal by Appellants, the determination of whether the Appellants satisfied the
relevant criteria is a decision left by law to Cambridge. 207 CMR 4.04. As demonstrated by
the City's denial of its transfer request, Appellants soundly failed to meet these
requirements.
AT&T cannot refute Cambridge's ability to inquire into the transferee's management
experience in determining whether a to grant a transfer request. See 207 CMR 4.04.
Here, AT&T has admitted that it, as transferee, does not possess the requisite
experience to operate a cable system in Massachusetts. Throughout the public hearing,
AT&T referenced the management of MediaOne as providing the necessary leadership for
this undertaking. See Cambridge Hearing attached as Exhibit D. In its subsequent
response to the Cambridge Request for Information, AT&T was again forced to admit this
fact.
Follow-up Question 1:
Q. Has AT&T ever managed any cable systems in Massachusetts? If so, which
systems and during what period of time?
A. No.
See MediaOne/AT&T Response to the Cambridge Request for Information
(September 10, 1999) attached as composite Exhibit E.
In light of this inexperience in the operation of cable systems, AT&T purports to
rely upon its own experience in communications generally, the "embedded
expertise" of the TCI management, and the MediaOne management structure that would be
retained following the merger. See Appellants Memorandum at 23. Only the first is
relevant to a transfer decision in Massachusetts, however.
Recent history justifies Cambridge's concern. In 1996, Magistrate Beard served the same
role in US West's takeover and transfer of cable licenses held by Continental. As here,
Magistrate Beard found the requisite management experience in US West's maintenance of the
Continental personnel. See Summary of Proceedings and Magistrate's Report (July 16,
1996) at 6-7 attached as Exhibit V. Soon thereafter, however, the large majority of
Continental management was either transferred to another region or released. This
highlights the fact that in such corporate mergers today, plans for retaining the
management of the purchased company are often temporary, are frequently a necessary
posturing for approval, and are not a reliable basis for judging management experience in
this context. Therefore, under the most limited interpretation of an Issuing Authorities'
discretion pursuant to Division's regulation, Cambridge's denial of the transfer due to
AT&T's lack of management experience is a legitimate concern, is certainly not
arbitrary or unreasonable and must be upheld.
Furthermore, AT&T's reliance upon MediaOne's management only strengthens
Cambridge's grounds for denial. AT&T misinterprets the City's demand for license
compliance as an attempt to amend the Agreement. On the contrary the Agreement as written
provides:
For the purposes of determining whether it shall consent to such a change in control
and ownership, the City may inquire into
all matters relative to whether such
Person is likely to adhere to the terms and conditions of the Final License
Cambridge License, §2.2(d) (emphasis supplied) (Exhibit N).
Along these same lines,
The consent of the Issuing Authority to a Transfer of the Final License shall not be
given if it appears from the application or from subsequent investigation that
(2)the License will not be adhered to
Cambridge License, §2.2(h) (emphasis supplied) (Exhibit N).
Thus, Cambridge expressly reserved the right to deny a transfer request when it
appeared that the License would not be adhered to by the transferee. The long list of
compliance issues presented to AT&T by the City establishes the fact that the license
was not being adhered to by MediaOne and its current management. Instead of demonstrating
the change needed, AT&T's attempts to rely upon this same management to demonstrate
its ability undermines its argument that it maintains the management experience. In this
case, the same wrong twice applied, i.e. MediaOne management, does not make a right.
AT&T's attempt to dismiss this basis as superficial is also inconsistent with the
history of this matter. Compliance with the existing license was of paramount importance
throughout. One week after the hearing, counsel for Cambridge sent a follow-up set of
questions that he perceived as not fully addressed at the hearing. See August 26,
1999 correspondence attached as composite Exhibit E. In the correspondence, Cambridge
listed a total of fifty-four (54) areas in which MediaOne management had failed to comply
with the existing license.
After AT&T refused to respond to these issues, Cambridge again on November 2, wrote
to MediaOne indicating nine sections of the license suffering from non-compliance and
requesting assurance that these failures would be remedied. See November 2, 1999
correspondence attached as composite Exhibit E. MediaOne, in its reply, confirmed that
these remained outstanding problems and that they were working towards their resolution. See
November 10, 1999 correspondence included in composite Exhibit E. Thus, it is apparent
that Cambridge's decision, in large part based upon uncertainty of the transferee's
compliance to perform under the existing license, was certainly not unreasonable or
arbitrary and therefore must withstand review by the Division.
Conclusion
For the foregoing reasons, the Division should deny MediaOne and AT&T's appeal of
the Issuing Authorities' decisions concerning AT&T's Requests for Transfer. The
Appellants fall short of meeting their burden for summary disposition. In addition, the
record establishes that consideration of open access by the Issuing Authorities in this
decision is appropriate. Accordingly, the Division regulations must be interpreted to
allow for this consideration of open access or the regulations must fall.
Hearings and deliberations consistent with this conclusion are necessary and requested.
Respectfully submitted,
City of Cambridge,
Town of North Andover,
City of Quincy,
City of Somerville,
by their counsel,
Charles R. Nesson
1575 Massachusetts Avenue
Cambridge, MA 02138
(617) 495-4609
nesson@law.harvard.edu
Kevin P. Conway
Conway, Crowley & Homer, P.C.,
332 Congress Street, Boston, MA
BBO# 097240.
Dated: December ___, 1999
|